Journal Articles

Evaluation of combined pre- and post-excavation grouting for reducing water inflow under high water pressure condition

Mikake, Shinichiro; Ikeda, Koki; Matsui, Hiroya; Tsuji, Masakuni*; Nishigaki, Makoto*

Doboku Gakkai Rombunshu, C (Chiken Kogaku) (Internet), 74(1), p.76 - 91, 2018/03

Pre-grouting of shafts and galleries had been conducted during the construction of MIU in the aspect of reducing water inflow. After excavating GL.-500m gallery, a post-grouting was performed on section of the pre-excavation grouting area under high water pressure condition (max: 4MPa). The post-grouting experiment was performed outside of the pre-grouting zone with designs, applying colloidal silica grouting material and complex dynamic grouting. It was estimated that the inflow after post-grouting was reduced by 1/100 of the case that pre- and post-grouting were not performed. These results indicate that the applied combined pre- and post-grouting methodology is effective in reducing water inflow and it can be applicable under high water pressure condition. Then, this paper states the theoretical evaluation of relationship between reduction of hydraulic conductivity and the grouting zone is very convenient and useful for grouting design and estimate of water inflow.

Journal Articles

Grouting design, results and evaluation of a gallery at great depth in Mizunami Underground Research Laboratory

Tsuji, Masakuni*

Doboku Kuotari, Vol.190, p.51 - 74, 2016/05

Pre-excavation grouting of shafts and galleries has been conducted during the construction of Mizunami Underground Research Laboratory in the aspect of safe works and reducing the discharge treatment of the water inflow. The grouting methodology has been simultaneously studied and developed as there is less experience of grouting in low conductive rock with high water pressure, especially in Japan. After excavating GL.-500m gallery on the ventilation shaft side, a post-excavation grouting campaign was performed on a 16-meter section of the pre-grouted area. Three new options for the grouting design were adopted and found to be effective with sufficiently decreasing the water inflow into the gallery.